Monday blackout due to human error – Dullas

Minister of Power Dullas Alahapperuma has told Cabinet yesterday (19) the reason for the nationwide blackout on Monday (17), was due to a mistake made by an official at Kerawalapitiya Grid Substation.
The Minister said the error led to the malfunctioning of the Grid Substation.
He informed the Cabinet that a report compiled by a committee under his purview to probe the incident would be handed over to him on 24 August. Alahapperuma also noted that similar blackouts had taken place on four previous occasions and stressed that he would brief the country regarding the recommendations that will be submitted to him by the committee, to prevent similar power outages in the future.
He added that repairs to Norochcholai Power Plant were continuing apace and the CEB is hopeful of restarting the plant by 24 August when it will add 600 megawatts to the National Grid.
He expressed hope that there would be no need for the scheduled islandwide power cuts to continue after 24 August.
(Source: Ceylon Today – By W.K. Prasad Manju)
Latest Headlines in Sri Lanka
- Nalanda College OBA donates flood relief to Defence Ministry December 11, 2025
- Excise officer arrested for allegedly seeking Rs. 2 Million bribe December 11, 2025
- Five suspects arrested in Dehiwala over planned retaliatory killing December 11, 2025
- Former Central Bank Governor Ajith Nivard Cabraal acquitted in Greek Bond case December 10, 2025
- Rebuilding Sri Lanka program receives LKR 1,893 Million for cyclone relief December 10, 2025


he is not a Engineer how can he state such a idiotic statement
Of course, he is not an Engineer, Engr Perera, but he a know-all Politician elected by the voters.
Mr Minister,
If true, how will you make sure it will not happen again?
I am surprised, one error by one official can plunge a Nation into darkness.